First Flexible DC Transformer Shipped for Xiang-Qian Power Flexibility Interconnection Project

On October 28, a 320-ton flexible DC transformer departed from Hengyang, Hunan, embarking on a journey of approximately 1,534 kilometers to the Xiang-Qian Power Flexibility Interconnection Project site in Tongren, Guizhou — an estimated 15-day transit.

The Xiang-Qian Power Flexibility Interconnection Project is a key initiative implementing China’s new energy security strategy and promoting cross-regional power coordination. The project involves constructing a 3,000 MW flexible DC back-to-back converter station in Tongren City, Guizhou Province, requiring a total of 13 flexible DC transformers. Each converter transformer measures 10 meters in length, 4 meters in width, and 4.7 meters in height. All 13 transformers will be transported via a combined road-rail method.

The highway transport section carries a total vehicle and cargo weight of 528 tons, marking the heaviest oversized road transport recorded in Guizhou Province, presenting severe challenges to road bearing capacity, bridge passage, and transport organization.

To ensure the safe delivery of this “national heavy equipment”, the convoy adopted a transport organization strategy of “segmented control, full-route escort, fixed-point monitoring, and digital oversight”. China Southern Power Grid’s EHV Company conducted advance review of oversized transport plans, performed individual survey and testing of roads and bridges along the route, calculated reinforcement requirements, cleared obstacles, and completed six rounds of simulated transport.

Digital methods were also integrated into transport safety management. Each flexible DC transformer is equipped with an on-board terminal that monitors vehicle trajectory, three-dimensional impact acceleration, inclination angle, and nitrogen pressure in real time. All data feeds into the company’s major project digital supply chain control platform, enabling full-process remote monitoring of transport trajectories, equipment status, and anomaly alerts. When parameters exceed limits or trajectories deviate during transport, early warnings are pushed immediately and coordinated with on-site response, forming a closed-loop operation of “online monitoring and offline handling”.

The first batch of 3 flexible DC transformers is expected to arrive in Tongren, Guizhou by the end of November, with the remaining 10 transformers arriving in batches according to on-site installation progress, providing solid material assurance for the project’s on-time commissioning.

Source: BJD Power Distribution Network (BJX)
Link: https://news.bjx.com.cn/html/20261104/1518863.shtml
Date: 2026-11-04


Source:BJD Power Distribution Network (BJX)