Unit 2 of State Grid Xinyuan Qujiang Pumped Storage Power Station Enters Commercial Operation in Zhejiang

On October 31, Unit 2 of the State Grid Xinyuan Zhejiang Qujiang Pumped Storage Power Station (referred to as “Qujiang Pumped Storage Power Station”) was officially put into commercial operation, joining the previously commissioned Unit 1 in supporting the power supply task of the Zhejiang grid.

Unit 2 in the underground powerhouse of the Qujiang Pumped Storage Power Station
Inside the underground powerhouse of the Qujiang Pumped Storage Power Station

The Qujiang Pumped Storage Power Station is located in Huangtankou Township, Qujiang District, Quzhou City, Zhejiang Province. It is a project listed in the national 13th Five-Year Plan for renewable energy development and one of the first batch of “Thousand Projects, Ten Thousand Hundreds” (Qian Xiang Wan Yi) major projects in Zhejiang Province. With a total installed capacity of 1.2 million kilowatts, a designed annual power generation of 1.2 billion kilowatt-hours and a designed annual pumping consumption of 1.6 billion kilowatt-hours, the station is an important regulating power source for building the new-type power system, ensuring stable grid operation and promoting reliable consumption of new energy.

Commissioning of Unit 2 was completed in 37 days. Drawing fully on the proven experience of Unit 1, the commissioning optimized work-process sequencing and strengthened on-site control and dispatch coordination, efficiently completing 54 test items including generation-direction tests and grid-connection tests. During trial operation, Unit 2 achieved a 100% startup success rate in both the generation and pumping directions, with all key indicators meeting design requirements.

An O&M worker checks equipment in front of a monitoring panel
An O&M worker checks equipment operation at the station

Pumped storage power stations are technically complex and place high demands on the professional competence of operation and maintenance personnel, while the workforce at Qujiang station is relatively young and lacks extensive commissioning and O&M experience. To address this, State Grid Xinyuan East China Branch coordinated professionals from its commissioned stations and deployed its own backbone personnel to the front line at Qujiang to provide technical assistance. “When we commissioned Unit 1, we used this kind of on-site mentoring and coaching to help staff improve their professional skills through practice, while summarizing and reusing commissioning experience to help everyone avoid risks in advance, shifting commissioning management from ‘passive defect elimination’ to ‘active prevention and control’,” said Yang Zhongjie, director of the Production Management Center of State Grid Xinyuan East China Branch.

At present, unit operation and installation-commissioning tasks at the Qujiang station are advancing in parallel, placing higher demands on the station’s overall management and safety control. To ensure all work proceeds safely and steadily, the station has divided the site into three zones — “operation”, “commissioning” and “installation” — reinforced physical separation, and assigned dedicated crews responsible for each zone. The station strictly follows the “two tickets and three rules” system, carries out solid operation and maintenance of commissioned equipment, and strengthens risk pre-control to ensure all work advances safely and in an orderly manner.

Aerial view of the upper reservoir of the Qujiang Pumped Storage Power Station
Aerial view of the upper reservoir of the Qujiang Pumped Storage Power Station

Since Unit 1 was put into operation in September this year, the station has completed the summer peak power supply task and supported the power supply for the 18th Zhejiang Provincial Games. During operation, the station refined its duty arrangements, carried out strict equipment inspections, and strengthened emergency response and rapid handling capabilities, holding firm the bottom line of production safety and ensuring a reliable power supply. As of October 31, the station had cumulatively generated 75 million kilowatt-hours of electricity and consumed 100.67 million kilowatt-hours for pumping, fully exercising the peak-shaving, energy-storage and other regulating functions of its pumped storage units.

Two operators inspect equipment inside the powerhouse
Operators carry out equipment inspection at the station

The Qujiang Pumped Storage Power Station has installed four reversible pump-turbine generating motor units, each with a single-unit capacity of 300,000 kilowatts; installation and commissioning of Units 3 and 4 are currently advancing in an orderly manner. Once the station is fully operational, it will effectively optimize the power source structure of the Zhejiang grid, support the large-scale development of new energy, and ensure the safe and stable operation of the grid.


Source:China Energy News Network

← Guiyang and Gui'an Sign Strategic Framework Agreement with Guizhou Power Grid to Advance New Distribution System Planning Hebei Issues 14 Measures to Further Improve the Grid Investment and Construction Environment →