The General Office of the People’s Government of Hebei Province has recently issued the “Several Measures of Hebei Province for Further Improving the Grid Investment and Construction Environment”. The document sets out 14 measures in three areas — planning coordination, approval optimization and local coordination — to simplify grid project approvals, consolidate local responsibilities, shorten the time required for preliminary procedures, keep grid construction in order, accelerate grid infrastructure construction and support the building of a new-type power system. Under the notice, the governments of all cities (including Dingzhou and Xinji), the Xiong’an New Area Administrative Committee and relevant provincial departments are required to implement the measures in light of local conditions.

Strengthening Planning Coordination
At the planning level, the measures make clear that grid projects of all voltage levels are to be incorporated into the provincial special power plan and, as appropriate, into territorial spatial plans and municipal and county energy and power plans. Based on the power plan, land for grid facilities and power transmission corridors are to be laid out in territorial spatial plans in a coordinated way. Planning is also to be adjusted on a rolling basis: in principle, grid projects of 110 kV and above are subject to annual adjustment, and grid-connection works supporting power sources, railways and other parent projects are to be incorporated into the special power plan in a timely manner as those projects progress; as the special power plan is revised, newly added projects are to be incorporated into territorial spatial plans in a timely manner.
For key project management, the document supports the inclusion of eligible grid projects in the power plan into the provincial and municipal key project lists and the inclusion of grid projects of all voltage levels into the provincial major infrastructure project list, coordinating the demand of grid projects for new construction land, forest use and grassland use.
Optimizing Preliminary Approvals
At the approval stage, the measures set out specific arrangements across several areas.
For river-crossing approvals of transmission lines, new lines should cross rivers by the shortest possible route, and narrow rivers should be crossed in a single span wherever possible; where a single-span crossing at the shortest distance is genuinely impossible due to objective conditions, the angle requirements for crossing may be relaxed to a moderate extent for projects approved within the province, provided safety is ensured.
For access to ecological red lines, transmission line projects conforming to territorial spatial plans at or above the county level that are determined to be unavoidable are allowed to cross ecological protection red lines outside the core protection zones of nature reserves. Where new construction land is involved, the recognition of permitted limited human activities or the unavoidable-routing demonstration for major national projects is to be handled in accordance with regulations; where no new construction land is involved, no recognition opinion on limited human activities is required. Where nature reserves are crossed, relevant procedures must be completed in accordance with the law.
For forest land, cities are to guarantee annual forest-use quotas for grid projects included in the provincial major infrastructure project list, under a “review immediately upon submission, approve immediately upon review” approach; where a city’s quota is insufficient, the municipal forestry and grassland authority may submit a written request to the provincial Department of Forestry and Grassland for provincial-level coordination.
For land, forest and grassland approvals, joint approval of land use, forest use and grassland use for grid projects is to be implemented, with one-off site-selection demonstration and a “single window for entry and exit”. After obtaining the land pre-examination and site-selection opinion, grid projects may apply for advance land use in accordance with regulations to ensure construction can start. On the premise of protecting the legitimate rights and interests of farmers whose land is expropriated, relevant municipal and county governments are supported in carrying out preliminary expropriation work in parallel within the project land scope determined by the “one map”.
For approvals involving mineral resources, where a transmission line overlays mining rights as confirmed by investigation, the county-level government organizes the grid enterprise and the mining right holder to jointly select a qualified assessment organization. Where mineral exploration and extraction and the construction project do not affect each other, or the impact is minor and does not affect safety, a mutual non-interference agreement is signed, no overlay treatment is made and no compensation is given; where mineral exploration and extraction are affected, the county-level government organizes the two parties to confirm the compensation amount based on the assessment results and sign an overlay consent agreement.
For planning permits, substation projects built outside urban development boundaries may, according to actual conditions and management needs, have planning demonstration plans or detailed plans for individual plots prepared by the municipal or county natural resources authority, and after approval by the municipal or county government these serve as the basis for issuing construction project planning permits. For transmission and transformation projects, the state-owned construction land allocation decision, the construction land planning permit and the construction project planning permit are to be issued in parallel or in due procedure.
For environmental impact assessment, on the premise that prior EIA, environmental monitoring and environmental acceptance procedures are compliant, substation renovation and expansion projects whose total number of main equipment increases by no more than 30% of the original and that do not significantly increase adverse environmental impacts are not required to apply for a new EIA approval.
Strengthening Local Coordination and Support
For local coordination, the measures require that in every city and county, an official in charge take the lead in advancing grid projects, implementing project conditions, organizing the centralized handling of feasibility-study agreements and preliminary procedures, and helping resolve problems encountered, so that the cycle for site selection, route planning and agreement handling is shortened to within 2 months. City and county governments are to organize land expropriation, compensation and resettlement; the related costs are incorporated into the allocation price and paid by the grid enterprise in accordance with regulations. The comprehensive regional land price for expropriation is to be calculated based on actual conditions, and standards for compensation of above-ground attachments and young crops are to be updated and specified.
On the alignment of municipal facilities with power facilities, when newly building, rebuilding or expanding roads, bridges, tunnels and other municipal infrastructure, authorities at all levels are to organize grid enterprises to provide demonstration opinions during project planning and approval to promote coordinated use of space resources; grid projects may complete procedures such as road occupancy, green-space occupancy and water use, as well as temporary-permanent road procedures, based on approval documents.
On grid construction order, the document makes clear that land for planned grid infrastructure and transmission line corridors are to be protected, anti-grab announcements for grid projects are to be issued in a timely manner in accordance with regulations, and acts such as rushed planting, rushed building and obstruction are strictly prohibited. Protection during grid facility construction is to be strengthened, problems such as construction obstruction are to be organized and resolved, crimes of theft and damage to grid facilities are to be severely cracked down on, and public security issues affecting grid construction order are to be rectified.
Source:China Energy News Network